AGENDA

Finance and Performance Committee

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Susan Baty (Chairperson)

Jim Jefferies (Deputy Chairperson)

Grant Smith (The Mayor)

Adrian Broad

Leonie Hapeta

Gabrielle Bundy-Cooke

Lorna Johnson

Vaughan Dennison

Karen Naylor

Lew Findlay QSM

Bruno Petrenas

 

 

 

 

 

 

 


 

 

 


PALMERSTON NORTH CITY COUNCIL

 

 

 

 

Finance and Performance Committee MEETING

 

20 August 2018

 

 

 

Order of Business

 

NOTE:     The Finance and Performance Committee meeting coincides with the ordinary meeting of the Audit and Risk Committee meeting.  The format for the meeting will be as follows:

-             Audit and Risk Committee will open and adjourn immediately to resume following the    Finance and Performance Committee

 

-              Finance and Performance Committee will open, conduct its business and then close.

1.         Apologies

2.         Notification of Additional Items

Pursuant to Sections 46A(7) and 46A(7A) of the Local Government Official Information and Meetings Act 1987, to receive the Chairperson’s explanation that specified item(s), which do not appear on the Agenda of this meeting and/or the meeting to be held with the public excluded, will be discussed.

Any additions in accordance with Section 46A(7) must be approved by resolution with an explanation as to why they cannot be delayed until a future meeting.

Any additions in accordance with Section 46A(7A) may be received or referred to a subsequent meeting for further discussion.  No resolution, decision or recommendation can be made in respect of a minor item.

3.         Declarations of Interest (if any)

            Members are reminded of their duty to give a general notice of any interest of items to be considered on this agenda and the need to declare these interests.

 

4.         Public Comment

To receive comments from members of the public on matters specified on this Agenda or, if time permits, on other Committee matters.

(NOTE:     If the Committee wishes to consider or discuss any issue raised that is not specified on the Agenda, other than to receive the comment made or refer it to the Chief Executive, then a resolution will need to be made in accordance with clause 2 above.)

5.         Confirmation of Minutes                                                                                     Page 7

“That the minutes of the Finance and Performance Committee meeting of 18 June 2018 Part I Public be confirmed as a true and correct record.”  

6.         He Ara Kotahi Bridge Lighting                                                                           Page 15

Report, dated 6 August 2018 from the Leisure Assets Planner, Jason Pilkington.

7.         Quarterly Performance and Financial Report - Quarter Ending 30 June 2018 Page 27

Memorandum, dated 31 July 2018 from the Financial Accountant, Keith Allan and the Head of Community Planning, Andrew Boyle.

8.         Treasury Report for 12 months ended 30 June 2018                                     Page 123

Memorandum, dated 30 July 2018 from the Strategy Manager Finance, Steve Paterson.

9.         Committee Work Schedule                                                                              Page 135

   

 

 

 

 

 10.      Exclusion of Public

 

 

To be moved:

“That the public be excluded from the following parts of the proceedings of this meeting listed in the table below.

The general subject of each matter to be considered while the public is excluded, the reason for passing this resolution in relation to each matter, and the specific grounds under Section 48(1) of the Local Government Official Information and Meetings Act 1987 for the passing of this resolution are as follows:

 

General subject of each matter to be considered

Reason for passing this resolution in relation to each matter

Ground(s) under Section 48(1) for passing this resolution

11.

Minutes of the Finance and Performance Committee meeting - Part II Confidential - 18 June 2018

For the reasons setout in the Finance and Performance Committee minutes of 18 June 2018, held in public present.

 

This resolution is made in reliance on Section 48(1)(a) of the Local Government Official Information and Meetings Act 1987 and the particular interest or interests protected by Section 6 or Section 7 of that Act which would be prejudiced by the holding of the whole or the relevant part of the proceedings of the meeting in public as stated in the above table.

Also that the persons listed below be permitted to remain after the public has been excluded for the reasons stated.

Chief Executive (Heather Shotter), Chief Financial Officer (Grant Elliott), Acting Chief Infrastructure Officer (Ray McIndoe), Acting General Manager – Strategy and Planning (David Murphy), General Manager - Community (Debbie Duncan), Acting General Manager – Customer (Sheryl Bryant) Human Resources Manager (Wayne Wilson), General Manager - Marketing and Communications (Sacha Haskell), because of their knowledge and ability to provide the meeting with advice on matters both from an organisation-wide context (being members of the Council’s Management Team) and also from their specific role within the Council.

Legal Counsel (John Annabell), because of his knowledge and ability to provide the meeting with legal and procedural advice.

Acting Governance and Support Team Leader (Stuart McKinnon) and Committee Administrators (Penny Odell, Rachel Corser and Courtney Kibby), because of their knowledge and ability to provide the meeting with procedural advice and record the proceedings of the meeting.

 

[Add Council Officers], because of their knowledge and ability to assist the meeting in speaking to their report and answering questions, noting that such officer will be present at the meeting only for the item that relate to their respective report.

[Add Third Parties], because of their knowledge and ability to assist the meeting in speaking to their report/s [or other matters as specified] and answering questions, noting that such person/s will be present at the meeting only for the items that relate to their respective report/s [or matters as specified].

 

 

   


 

 

 


PALMERSTON NORTH CITY COUNCIL

 

 

Palmerston North City Council

 

Minutes of the Finance and Performance Committee Meeting Part I Public, held in the Council Chamber, First Floor, Civic Administration Building, 32 The Square, Palmerston North on 18 June 2018, commencing at 9.00am

Members

Present:

Councillor Susan Baty (in the Chair), The Mayor (Grant Smith) and Councillors Adrian Broad, Gabrielle Bundy-Cooke, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Karen Naylor and Bruno Petrenas.

Non Members:

Councillors Brent Barrett, Rachel Bowen, Duncan McCann and Aleisha Rutherford.

Apologies:

Councillor Tangi Utikere.

 

Councillor Vaughan Dennison entered the meeting at 9.10am during consideration of clause 48.  He was not present for clauses 44 to 47 inclusive.

 

44-18

Apologies

 

Moved Grant Smith, seconded Leonie Hapeta.

The COMMITTEE RESOLVED

1.   That the Committee receive the apologies.

 

Clause 44-18 above was carried 14 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

  

45-18

Late Item

 

Moved Aleisha Rutherford, seconded Karen Naylor.

The COMMITTEE RESOLVED

1.  That the late item `Papaioea Place Housing Redevelopment Construction Programme’ be received.

 

Clause 45-18 above was carried 12 votes to 2, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Lew Findlay QSM, Jim Jefferies, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

Against:

Councillors Leonie Hapeta and Lorna Johnson.

 

46-18

Confirmation of Minutes

 

Moved Gabrielle Bundy-Cooke, seconded Bruno Petrenas.

The COMMITTEE RESOLVED

1.   That the minutes of the Finance and Performance Committee meeting of 21 May 2018 Part I Public be confirmed as a true and correct record.

 

Clause 46-18 above was carried 12 votes to 0, with 2 abstentions, the voting being as follows:

For:

Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke,  Lew Findlay QSM, Leonie Hapeta, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

Abstained:

The Mayor (Grant Smith) and Councillor Jim Jefferies.

 

47-18

Palmerston North Airport Ltd - Final Statement of Intent for 2018/19

Memorandum, dated 5 June 2018 from the Strategy Manager Finance, Steve Paterson.

 

Moved Susan Baty, seconded Aleisha Rutherford.

The COMMITTEE RECOMMENDS

1.   That the Palmerston North Airport Ltd Statement of Intent for 2018/19 be endorsed.

 

Clause 47-18 above was carried 14 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

 

Councillor Vaughan Dennison entered the meeting at 9.10am.

 

48-18

Approval to Write Off Uncollectible Balances

Memorandum, dated 15 May 2018 from the Financial Accountant, Keith Allan.

 

Moved Jim Jefferies, seconded Rachel Bowen.

The COMMITTEE RECOMMENDS

1.   That Council approve the write off of bad debts totalling $44,857.05 (including GST) with removal from the accounts receivable ledger.

 

Clause 48-18 above was carried 14 votes to 1, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

Against:

Councillor Leonie Hapeta.

 

49-18

Fees & Charges - Confirmation Following Public Consultation

Memorandum, dated 8 June 2018 from the Strategy Manager Finance, Steve Paterson.

In discussion the Committee was of the view that the sign farm sites should be reviewed.

 

Moved Susan Baty, seconded Jim Jefferies.

The COMMITTEE RECOMMENDS

1.   That the submission from Aokautere Land Holdings Ltd be received and the officer’s comments in response, as outlined in Attachment A of the memorandum dated 8 June 2018 entitled `Fees and Charges – Confirmation Following Public Consultation’ be noted.

 

Clause 49.1 above was carried 15 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

 

2.   That the fees and charges for Planning & Miscellaneous Services, as scheduled in Attachments B and C of the memorandum dated 8 June 2018 entitled `Fees and Charges – Confirmation Following Public Consultation’, be approved, effective from 1 July 2018.

 

3.   That the fees and charges for Trade Waste Services, as scheduled in Attachment D of the memorandum dated 8 June 2018 entitled `Fees and Charges – Confirmation Following Public Consultation’, be approved, effective from 1 July 2018.

 

Clauses 49.2 to 49.3 above were carried 14 votes to 0, with 1 abstention, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

Abstained:

Councillor Leonie Hapeta.

 

Moved Susan Baty, seconded Grant Smith.

4.    That the Chief Executive review the sign farm sites.


 

 

Clause 49.4 above was carried 15 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

 


50-18

Papaioea Place Housing Redevelopment Construction Programme

Memorandum, dated 11 June 2018 from the Parks & Property Manager, John Brenkley.

 

Moved Susan Baty, seconded Karen Naylor.

The COMMITTEE RECOMMENDS

1.   That the Construction Programme for the Papaioea Place Housing Redevelopment Project be Received.

 

Clause 50-18 above was carried 15 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

 

51-18

Committee Work Schedule

 

Moved Susan Baty, seconded Rachel Bowen.

The COMMITTEE RESOLVED

1.   That the Finance and Performance Committee receive its Work Schedule dated June 2018.

 

Clause 51-18 above was carried 15 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

      

52-18

Minor Item

 

Moved Aleisha Rutherford, seconded Duncan McCann.

The COMMITTEE RESOLVED

That the minor item `Write Off Uncollectible Balances’ be received.


 

 

Clause 52-18 above was carried 15 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Brent Barrett, Susan Baty, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

 

Exclusion of Public

53-18

Recommendation to Exclude Public

 

Moved Aleisha Rutherford, seconded Leonie Hapeta.

The COMMITTEE RESOLVED

“That the public be excluded from the following parts of the proceedings of this meeting listed in the table below.

The general subject of each matter to be considered while the public is excluded, the reason for passing this resolution in relation to each matter, and the specific grounds under Section 48(1) of the Local Government Official Information and Meetings Act 1987 for the passing of this resolution are as follows:

 

General subject of each matter to be considered

Reason for passing this resolution in relation to each matter

Ground(s) under Section 48(1) for passing this resolution

11.

Minutes of the Finance and Performance Committee meeting - Part II Confidential - 21 May 2018

For the reasons setout in the Finance and Performance Committee minutes of 21 May 2018, held in public present.

12.

Award of Contract 3532 Installation of "V" Category LED Street Lighting Luminaires Stage 2

Third Party Commercial

s7(2)(b)(ii)

 

This resolution is made in reliance on Section 48(1)(a) of the Local Government Official Information and Meetings Act 1987 and the particular interest or interests protected by Section 6 or Section 7 of that Act which would be prejudiced by the holding of the whole or the relevant part of the proceedings of the meeting in public as stated in the above table.

Also that the persons listed below be permitted to remain after the public has been excluded for the reasons stated.

Chief Executive (Heather Shotter), Chief Financial Officer (Grant Elliott), General Manager, City Enterprises (Ray McIndoe), General Manager, City Future (Sheryl Bryant), General Manager, City Networks (Ray Swadel), General Manager, Customer Services (Peter Eathorne), General Manager, Libraries and Community Services (Debbie Duncan), Human Resources Manager (Wayne Wilson), General Manager, Marketing and Communications (Sacha Haskell), and Communications Advisor (name) because of their knowledge and ability to provide the meeting with advice on matters both from an organisation-wide context (being members of the Council’s Management Team) and also from their specific role within the Council.

Legal Counsel (John Annabell), because of his knowledge and ability to provide the meeting with legal and procedural advice.

Acting Governance and Support Team Leader (Stuart McKinnon) and Committee Administrators (Penny Odell and Rachel Corser), because of their knowledge and ability to provide the meeting with procedural advice and record the proceedings of the meeting.

Project Engineer (Rob Cuff) because of his knowledge and ability to assist the meeting in speaking to his report and answering questions, noting that such officer will be present at the meeting only for the item that relates to his report.

 

Clause 53-18 above was carried 15 votes to 0, the voting being as follows:

For:

The Mayor (Grant Smith) and Councillors Susan Baty, Brent Barrett, Rachel Bowen, Adrian Broad, Gabrielle Bundy-Cooke, Vaughan Dennison, Lew Findlay QSM, Leonie Hapeta, Jim Jefferies, Lorna Johnson, Duncan McCann, Karen Naylor, Bruno Petrenas and Aleisha Rutherford.

 

 

The public part of the meeting finished at 9.42am

 

Confirmed 20 August 2018

 

 

 

Chairperson

 

 



 

 

 


PALMERSTON NORTH CITY COUNCIL

 

Report

TO:                                Finance and Performance Committee

MEETING DATE:           20 August 2018

TITLE:                            He Ara Kotahi Bridge Lighting

DATE:                            6 August 2018

AUTHOR/S:                   Jason Pilkington, Leisure Assets Planner, Infrastructure

APPROVED BY:             Ray McIndoe, Acting Chief Infrastructure Officer

 

 

RECOMMENDATION(S) TO Council

1.   That Council approves $1,210,000 of unbudgeted funds to ensure the He Ara Kotahi Bridge is lit as per the Manawatū River Framework Lighting Plan, as described in Appendix I of the report titled “He Ara Kotahi Bridge Lighting”.

2.   That Council directs the Chief Executive to make funding applications up to $610,000 for the purchase and installation of lights on the He Ara Kotahi Bridge and Plaza area.

 

 


 

Summary of options analysis for

 

Problem or Opportunity

The Manawatū River Framework and Programme 1435 have budget to develop a lighting loop from the Fitzherbert Bridge along both banks of the Manawatū River to the He Ara Kotahi Bridge.

That budget did not include funds to ensure the new bridge has the capacity to be lit, or for lighting purchase and install costs.

Officers caught this oversight prior to the new bridge steel being fabriacted. The Chief Executive Officer approved the required variations to the existing bridge contacts, during July in the absense of Council meetings.

Officers were directed by the Chief Executive to report to Council as early as possible on options for funding the unbudgeted works, through either increased borrowings or making existing savings.   

OPTION 1:

Council approves $1,210,000 for lighting the He Ara Kotahi Bridge.

Officers will seek to fund $610,000 (approximately 50% of the total cost) of the light purchase and install phase of the project through external funding applications.

Community Views

The community has generally been very positive towards the establishment of a new pedestrian cycle-way.

Benefits

No requirement in the future to try and retrofit the new bridge for lighting, which would likely be more expensive and potentially unsightly.

Risks

Funding applications fall through and Council is required to fund the full cost of light purchase and install.  The Councils project investment coordinator advises the Central Energy Trust is the best funder for the river lighting project and the project may not fit the funding criteria of other funding organisations.  Also other applications will need to be carefully manged to not detract from other council projects

Financial

$1,210,000 in additional unbudgeted funding is required ($610,000 from external funds).

OPTION 2:

Council approves $1,210,000 for lighting the He Ara Kotahi Bridge, and funds the entire amount from borrowings.

Community Views

The community has generally been very positive towards the establishment of a new pedestrian cycle-way.

Benefits

This options means Council is not dependent on external funding to complete the project and lighting install and purchase can take place immediately.

Risks

Council already has a $350,000 funding application with Central Energy Trust, and early indications from the Board are positive.

Financial

$1,210,000 in additional unbudgeted funding is required.

OPTION 3:

Council approves $1,210,000 for lighting the He Ara Kotahi Bridge, and directs the Chief Executive to reallocate funds from existing infrastructure projects.

Community Views

The community has generally been very positive towards the establishment of a new pedestrian cycle-way.

Benefits

This option does not require Council to fund the project through increasing borrowing.

Risks

Other infrastructure projects would be sacrificed to fund the bridge lighting, and these projects would need to be reconsidered at the next 10 Year Plan. Therefore the saving may only be a deferral of works.

Financial

No additional finance required on this option.

The recommendations contribute to Goal 2: A creative and exciting city

The recommended option contributes to the outcomes of the Creative and Liveable Strategy

The recommended option contributes to the achievement of action/actions in the Active Community Plan

The action is: Construct a centrally located lit 3-4 km walking circuit to enable safe, night time walking and exercise during evenings and winter (e.g. between the River bridges once the He Ara Kotahi bridge built) (by end of 2022/2023).

Contribution to strategic contribution

This proposal will ensure that one key link in this Plan is not missed – lighting the He Ara Kotahi Bridge in order to develop the full 3-4 km lighting link.

 

Rationale for the recommendations

1.         Overview of the problem or opportunity

1.1       During the 2018-2028 10 Year Plan process two programmes related to lighting in the Manawatū River area were put up to Council for consideration – Programmes 1435 (River Lighting Loop) and 752 (Manawatū River Framework). The programme 1435 for a lighting loop came from an action in the Active Communities Plan. 

1.2       Programme 752 Manawatū River Framework committed $495,000 to lighting the Fitzherbert Bridge. Programme 1435 Manawatū River Lighting Loop committed $420,000 towards lighting both river banks (Victoria Esplanade side and the Massey University side) from the Fitzherbert Bridge to the new He Ara Kotahi bridge. 

1.3       It was mistakenly assumed by Officers at that time that the He Ara Kotahi Bridge was planned to have lighting and that the lighting would be covered by the He Ara Kotahi Bridge budgets.

1.4       Once this oversight was discovered, Officers moved quickly to establish both a lighting plan for the bridge and ensure that the build and fabrication of the new bridge would at least have the capacity to be lit in accordance with the lighting plan.

1.5       Council was away in July 2018, and no reports could be put forward seeking approval for the funding and the work. Officers worked with the acting Chief Infrastructure Officer and the CEO to find an adequate solution. It was decided to approve the variations to the contract so as to avoid future additional costs, then report to Council accordingly – so as not to miss the only available window of opportunity.

1.6       Since that time Officers have sought an appropriately skilled sub-contractor, made the appropriate variations to the bridge contracts and submitted an application to Central Energy Trust for light purchase and install costs. 

2.         Background and previous council decisions

2.1       During the development of the Manawatū River Framework in 2016 a budget was established under that plan for lighting a section of the Manawatū River – predominantly along the City side edge in the vicinity of the Victoria Esplanade river bank. The aerial below describes the original river section (in orange) to be lit.

2.2       During the development of the Active Communities Plan in 2017 further consideration was given to lighting, and it was proposed to develop a full lighting loop – from the Fitzherbert Bridge to the new He Ara Kotahi Bridge.  The aerial below shows the full lighting loop (in green) as proposed and adopted through adoption of the Active Communities Plan. 

2.3       The Fitzherbert Bridge, Massey University bank and Victoria Esplanade bank were then budgeted and those budgets included in the draft 2018-2028 10 Year Plan. This plan was adopted, along with these budgets, in June 2018.

2.4       The design work for the Manawatū River Framework was undertaken in the 2017/18 financial year with the desire to pull all design-work together up-front in a single year. The lighting design began towards the end of the 2017/18 financial year, as one of the last pieces of design work.

2.5       Once Officers began planning and design for lighting the entire loop (under the Manawatū River Framework design) in 2017/18 it was discovered that there was no plan for He Ara Kotahi Bridge lighting, or provision made for lighting on the bridge itself.

2.6       The cost of the full lighting loop – which includes lighting on the Fitzherbert Bridge, the Massey bank, the Victoria Esplanade bank and the He Ara Kotahi Bridge is $2,125,000.

2.7       This is broken down in the following table (note: yellow is non-budgeted lighting work):

Feature

Phase

Cost

He Ara Kotahi Bridge Lighting (Total cost)

Phase 1

$1,210,000

Fitzherbert Bridge Lighting

Phase 2

$495,000

Victoria Esplanade bank lighting

Phase 3/4

$210,000

Massey University bank lighting

Phase 3/4

$210,000

Total

 

2,125,000

 

2.8       In the table above only the Phases 2-4 were funded through Programmes 752 (Manawatū River Framework) and 1435 (Manawatū River Lighting Loop) in the 2018-2028 10 Year Plan. The He Ara Kotahi Bridge lighting at Phase 1 was not included in either of these programmes.

2.9       The knowledge of the above oversight occurred at the same time that the fabrication work for the new He Ara Kotahi Bridge was beginning to kick off – in April 2018.

2.10     Officers worked with the lighting designers, electrical engineers, the bridge contractors and the fabricators to establish whether a solution could be formed in time. Once it was established that a solution could be achieved and a cost for the additional work was established, Officers approached the CEO in order to assess the situation with regards funding.

2.11     During this work Officers identified what work would need to be funded and completed immediately, and what work could wait. There were a number of features that required immediate attention:

·    Establishing power along the underside of the bridge to the Massey side.

·    Modification of the bridge steel work so that the bridge would have the capacity to hold lights (as per the lighting design).

·    Laying of the ducting in the Plaza area for lighting to be installed at a later date.

2.12     There were a number of features that could potentially wait:

·    Purchase of actual lights.

·    Install and laying of electrical cable.

2.13     The yellow section of the table above (He Ara Kotahi lighting) is split into two distinct aspects. They are:

·    $600,000 (To fabricate lighting infrastructure into the bridge, power to Massey side and lay ducting for lighting capacity – required immediately)

·    $610,000 (To purchase lights and pay for install – not required immediately)

2.14     It was accepted that an executive decision needed to be made immediately for the features listed in 2.11 of this report, because an instruction to the Bridge Contractor needed to be issued no later than 10 July 2018, and there was no opportunity during July to seek formal Council approval before that date.

2.15     The consequences of not issuing an instruction to the bridge contractor would have been:

·    Higher cost to try and retrofit lighting at a later stage (significant replacement of metal railings, posts and handrails).

·    Potentially an inferior lighting solution to the one proposed at Palmerston North’s premier river section and park area, in order to try and cut costs. This outcome would look completely out of place given the high quality plans for the Fitzherbert Bridge and river bank areas leading into the new bridge.

·    Potentially unsightly cables and ducting on the bridge if a retrofit was able to be achieved.

·    Potentially unsafe pedestrian/walkway that has no lighting at night.

2.16     With the above in mind the Chief Executive directed Officers to issue the instruction to make the relevant variations to the bridge contract, and directed officers to report to the nearest appropriate Committee with options and recommendations.

3.         Description of options

3.1       Option 1: Council approves $1,210,000 for lighting the He Ara Kotahi Bridge. Officers will seek to fund $610,000 (approximately 50% of the total cost) of the light purchase and install phase of the project through external funding applications.

3.2       Option 2: Council approves $1,210,000 for lighting the He Ara Kotahi Bridge, and funds the entire amount from borrowings.

3.3       Option 3: Council approves $1,210,000 for lighting the He Ara Kotahi Bridge, and directs the Chief Executive to reallocate funds from existing infrastructure projects.

4.         Analysis of options

4.1       Option 1: Council approves $1,210,000 for lighting the He Ara Kotahi Bridge. Officers will seek to fund $610,000 (approximately 50% of the total cost) of the light purchase and install phase of the project through external funding applications.

4.2       There are a number of issues that could have emerged, had the instruction from the Chief Executive to create the variations to the contract for He Ara Kotahi Bridge not gone ahead. They are:

·    An expensive retrofit. The lighting design incorporates lighting fixtures that are not visible to the eye, and are hidden within the bridge infrastructure (such as in handrails, etc.). This creates a subtle, high quality lighting effect. It is likely that cutting out steel, posts and handrails and adding in new ones after the fact would at least double the cost on install.

·    If the retrofit costs for install to the design plan were too inhibitive, Council could end up with unsightly cables and ducting running along the bridge to try and achieve the same effect. This would significantly reduce the aesthetic amenity of design that Council has worked hard to achieve on this project.

·    If retrofit to the design was simply no longer possible, which is likely for some of the lighting proponents; the cost was too prohibitive or the results too unsightly, Council may have ended up with a high quality bridge with poor lighting outcomes at night and something inconsistent with the rest of the planned river lighting loop.

·    By entering into a commitment to light this portion of the river network in the Active Communities Plan and the 2018-2028 10 Year Plan, Council has committed to providing a safe, quality night-time experience in this area. Not lighting this bridge, or poor lighting, would be inconsistent with the Active Communities Plan, the 10 year Plan and the aesthetic lighting plan for the area.

4.3       Officers have lodged a funding application with Central Energy Trust for funding parts of the lighting purchase and install costs, as per the Trust’s criteria. So far early discussions with the Trust have been positive.

4.4       There are also other funding options with regards covering costs for lighting purchase and install costs. Officers are currently seeking external funds, and will report back to Council in September on the status of funding applications for this project.

4.5       Option 2: Council approves $1,210,000 for lighting the He Ara Kotahi Bridge, and funds the entire amount from borrowings.

 

4.6       The analysis of Option 1 holds for this option.

4.7       This option requires Council to fund the full amount of the project - $1,210,000. Currently Council has an application with Central Energy Trust for $450,000, and early discussions with the Board are positive. A successful application would still see a funding shortfall of $160,000.

4.8       Under this option Officers could potentially make up as much of the additional funding required for the project from external funds and then report on any shortfalls with recommendations in September 2018.

4.9       Option 3: Council approves $1,210,000 for lighting the He Ara Kotahi Bridge, and directs the Chief Executive to reallocate funds from existing infrastructure projects.

4.10     The analysis for Option 1 holds for this option.

4.11     This option would require Officers to go through budgets and establish which programmes could potentially undergo some reallocation of budget in order to fund the bridge lighting.

4.12     This option will mean that an existing programme(s) will need to be halted or partially completed until such time as additional budget is available for the work.

4.13     Given that much of the work Council engages in is necessary this option may in reality only see a deferral of cost to the next 10 Year Plan funding round.   

5.         Conclusion

5.1       Council has produced a high quality decorative and practical lighting design as part of the Manawatū River Framework and the Active Communities Plan, for a lighting loop in the Victoria Esplanade river environment. 

5.2       During this design work it was discovered that Officers had overlooked whether lighting for the He Ara Kotahi Bridge was in fact funded through the He Ara Kotahi project. It was not.

5.3       Once the oversight was discovered officers worked to deliver to suitable solution to ensure the bridge would have the capacity to be lit.

5.4       This occurred while Council was away, and the Chief Executive directed Officers to report to Council on the matter as a soon as practicable.

6.         Next actions

6.1       Fabrication of the bridge for lighting and laying of ducting occurs.

6.2       Resource consent for lighting.

6.3       Develop funding applications for install and purchase of lights.

6.4       Report back to Council on the outcome of the project in September 2018.

7.         Outline of community engagement process

7.1       This lighting project went through a community engagement process consistent with that completed during the Active Communities Plan and the 2018-2018 10 Year Plan.

Compliance and administration

N/A

 

Does the Committee have delegated authority to decide?

If Yes quote relevant clause(s) from Delegations Manual <Enter clause>

No

Are the decisions significant?

No

If they are significant do they affect land or a body of water?

No

Can this decision only be made through a 10 Year Plan?

No

Does this decision require consultation through the Special Consultative procedure?

No

Is there funding in the current Annual Plan for these actions?

No

Are the recommendations inconsistent with any of Council’s policies or plans?

No

 

 

 

 

 

Attachments

1.

Manawatū River Lighting design

 

    


 

 



 

 

 


PALMERSTON NORTH CITY COUNCIL

 

Memorandum

TO:                                Finance and Performance Committee

MEETING DATE:           20 August 2018

TITLE:                            Quarterly Performance and Financial Report - Quarter Ending 30 June 2018

DATE:                            31 July 2018

AUTHOR/S:                   Keith Allan, Financial Accountant, Finance

Andrew Boyle, Head of Community Planning, Strategy and Planning

APPROVED BY:             Grant Elliott, Chief Financial Officer

David Murphy, Acting General Manager - Strategy and Planning

 

 

RECOMMENDATION(S) TO Council

1.       That the Committee receive the June 2018 Quarterly Performance and Financial Report and note:

a.    The June 2018 financial performance and operating performance.

b.    The June 2018 capital expenditure programme progress together with those programmes identified as unable to be completed this financial year.

2.       That the Committee note that the capital expenditure carry forward values in the 2018/19 Annual Budget will be increased by a net $674,100 to the amount of remaining programme budgets.

 

 

 

 

1.         ISSUE

To provide a quarterly update on the performance and financial achievements of the Council for the period ending 30 June 2018. This is the fourth quarterly report for the year.

 

2.         BACKGROUND

As this is the final report for 2017/18 it is reported against the activities relating to that year. Future reports will be against the new goals as detailed in the 10 Year Plan 2018-28.

 

Cost of services delivered year to date:

-     Operating-controllable variance

-     Variance with interest and rates included

 

 

($0.9m) unfav

$0.7m fav

Services are being delivered within budget with some higher revenues received (part with higher offsetting costs), a reduced call for some service delivery costs, reduced by unbudgeted costs incurred.

Percent of full year capital expenditure budget completed:

-     Renewal

-     New

-     Total

 

Total completed year to date:

 

 

86.5%

61.6%

70.6%

 

$48.8m

Compares with amounts completed same time in 2016/17:

81.9%

49.0%

63% completed full year.

Expenditure value 47% higher than last year.

$33.1m

Operating cash flows variance to budget

$8.1m fav

Favourable to budget with favourable operating variance and a lower working capital requirement to that budgeted.

Increase in net debt

$24.1m fav

Lower due to favourable operating variance, lower working capital and lower capital expenditure. Note a significant amount of this is timing only and will be utilised when accounts payable are paid.

 

3.         NEXT STEPS

Details of operating and financial performance are included in the following sections.

4.         Compliance and administration

Does the Committee have delegated authority to decide?

If Yes quote relevant clause(s) from Delegations Manual <Enter clause>

No

Are the decisions significant?

No

If they are significant do they affect land or a body of water?

No

Can this decision only be made through a 10 Year Plan?

No

Does this decision require consultation through the Special Consultative procedure?

No

Is there funding in the current Annual Plan for these actions?

No

Are the recommendations inconsistent with any of Council’s policies or plans?

No

The recommendations contribute to Goal 5: A driven and enabling Council

 

The recommendations contribute to the outcomes of the Driven and Enabling Council Strategy

 

The recommendations contribute to the achievement of action/actions in a plan under the Driven and Enabling Council Strategy

The action is: to enable Council to exercise governance by reviewing financial performance and operating performance and provide accountability for these to the public.

 

Contribution to strategic direction

As above

 

 

 

Attachments

1.

Section one, two June Quarterly Performance and Financial Report

 

2.

Section three June Quarterly Performance and Financial Report

 

    


PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator



PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator



 

 

 


PALMERSTON NORTH CITY COUNCIL

 

Memorandum

TO:                                Finance and Performance Committee

MEETING DATE:           20 August 2018

TITLE:                            Treasury Report for 12 months ended 30 June 2018

DATE:                            30 July 2018

AUTHOR/S:                   Steve Paterson, Strategy Manager Finance, Finance

APPROVED BY:             Grant Elliott, Chief Financial Officer

 

 

RECOMMENDATION

1.   That the performance of the treasury activity for the 12 months ending 30 June 2018 be noted.

 

 

 

1.         ISSUE

            To provide an update on the Council’s treasury activity for the 12 months ended 30 June 2018.

2.         BACKGROUND

2.1       Investment Fund

 

In November 2008 Council endorsed an orderly exit strategy for the Fund which embraced holding the investments in bonds to maturity or when they could be sold without realising a loss (i.e. if the yields fall below the purchase price).

 

This strategy has been encapsulated in subsequent 10 Year and Annual Plans and the realisation process was completed in December 2017.

2.2       Term Debt

The Council’s Annual Budget for 2017/18 forecast additional debt of $19m would need to be raised during the year to fund the $39.5m of new capital expenditure programmes (including assumed carry forwards from 2016/17).  In June 2017 the Council resolved to specifically authorise the raising of up to $19m of additional debt. 

Council’s Financial Strategy (updated version adopted 24 June 2015) contains the following ratios which the Council has determined to be prudent maxima:

•   Net debt as a percentage of total assets not exceeding 20%

•   Net debt as a percentage of total revenue not exceeding 175% 

•   Net interest as a percentage of total revenue not exceeding 15%

•   Net interest as a percentage of annual rates income not exceeding 20%

The Treasury Policy (embracing the Liability Management and Investment Policy), updated in December 2017, also contains a number of other criteria regarding debt management.

 

(Note: on 25 June 2018 the Council adopted its updated financial strategy and 10 Year Plan 2018-28.  They contain an amended maxima for the future of 200% for the net debt to total revenue ratio.)

 

Following the latest annual review published on 9 April 2018 Council’s S&P Global Rating’s credit rating remains unchanged at AA / A-1+. 

 

3.         Performance

 

3.1       Investment Fund

 

The Fund had a balance of $2.71m at 1 July 2017 and was fully realised in December 2017.  Movements in Fund value are shown in the following graph:

 

 

Realised Fund earnings from interest and dividends for the 6 months totalled $30k.  $2.78m was distributed back to the Council during the period including $2.75m of maturing investments.

 

 

 

3.2       Term Debt

 

Schedule 1 attached shows the details of Council’s debt as at 30 June 2018.   Debt levels were within the policy parameters outlined in clause 2.2. of this report.

The summarised gross term debt movements are shown in the following table:

 

Annual Budget for year (2017/18)

$000

Actual – 3 months (2017/18)

$000

Actual – 6 months (2017/18)

$000

Actual – 9 months (2017/18)

$000

Actual – 12 months (2017/18)

$000

Debt Balance at 1 July 2017

New Debt #

Debt repayments #

101,600

19,000

 

97,000

12,000*

 

97,000

12,000

12,000

97,000

17,000**

12,000

97,000

19,875

17,000

Closing Balance at 30 June 2018

Comprising:

Bank advance (on call)

LGFA short term advance

LGFA & Council stock

120,600

109,000

 

 

10,000

99,000

97,000

 

 

10,000

87,000

102,000

 

 

10,000

92,000

99,875

 

2,875

10,000

87,000

 

#   A portion of the Council’s debt is drawn on a daily basis – daily drawdowns & repayments are not included in these figures but the net draw or repayment for the year to date is shown as part of new debt or debt repayment as appropriate.

*   $12m new debt was raised in August to pre-fund debt maturing in December 2017.  The sum was placed on short term deposit in the interim. 

** $5m of new debt was raised in March to pre-fund debt maturing in May 2018.  This sum was also placed on short term deposit in the interim. 

Overall the interest income will more than cover the interest cost of the sums funded in advance.

Net debt at 30 June 2018 was $98.875m (ie gross $99.875m less short term deposits of $1.0m) compared with $93.665m at 1 July 2017 (i.e. gross $97m less investment fund of $2.71m and call investment of $0.625m).

Council’s Treasury Policy prescribes under the counterparty credit risk section that investments for any registered bank will not exceed $10m.  As at 30 September 2017 $16.25m was invested with Westpac - $12m of this related to the pre-funding of debt maturing in December 2017.  The investment level returned within policy parameters before 31 December 2017. 

 

 

 

 

 

Movements in recent years are shown in the following graph:

Actual finance costs incurred during the 12 months (including interest, line fees & the effects of swaps) amounted to $5.846m compared with the budget for the year of $6.462m. 

The Council has entered a number of financial instruments related to its debt portfolio utilising swap trading lines established with Westpac and ANZ.  The details of these are shown in Schedule 2 attached.

The value of these instruments is measured in terms of its “mark-to-market” i.e. the difference between the value at which the interest rate was fixed and the current market value of the transaction.  Each of these transactions was valued at the date they were fixed and again at the reporting date.  Financial reporting standards require the movement in values to be recorded through the Council’s Statement of Comprehensive Income (Profit & Loss Account).  They have been revalued as at 30 June 2018 and show an increase in book value of $212k for the quarter, but a reduction of $165k for the year.

The Council’s Treasury Policy contains guidelines regarding the measurement of treasury risk as follows:

·    Interest rate risk is managed by the Council maintaining the ratio of debt that is subject to floating versus fixed interest rates within pre-set limits.

·    Funding and liquidity risk is managed by the Council maintaining a pre-set portion of its debt in a range of maturity periods eg < 1 year, 1 – 3 years, 5 years +. 

The position compared to the policy is illustrated in the graphs in Schedule 3.  The overall ratio of fixed v floating interest rate debt is based on the assessed level of total debt in 12 months’ time.  During 2017/18 we used a rolling 12 month projection of $105m for this assessment.  This is considerably less than assumed in the Annual Budget and reflects that actual capital expenditure (and as a consequence total debt) is less than the budget assumption.  The projection for reporting for 2018/19 has not yet been finalised as it relies on more detailed assessment of the timing of planned capital expenditure.  The interest rate risk position graph shows that based on forecast debt of $105m, then 78% of the interest exposure is fixed.  However the budget for 2018/19 assumes $39m of additional debt will need to be raised during the year.  If this forecast is used for this policy then 59% of interest is currently fixed.  The policy requires that at least 55% is fixed. 

As at 30 June 2018 all of the policy targets had been met. 

Council’s credit lines with the banks include a $18m four year credit facility with Westpac Bank (maturing 31 July 2020) and a revolving $25m three year facility with ANZ Bank (maturing 31 March 2021).

4.         CONCLUSION & NEXT STEPS

Realised interest and dividend returns for the 12 months from the Fund of $30k equates the budget.  Finance costs for the 12 month period (including interest, line fees & the effect of swaps) was $5.846m compared with budget for the year of $6.462m.

 

In conjunction with Council’s treasury advisors hedging instruments are regularly reviewed in an effort to ensure the instruments are being utilised to best advantage as market conditions change. The level of hedging cover is also reviewed as the forecasts of future debt levels are revised.

 

Council’s borrowing strategy is continually reviewed, in conjunction with Council’s treasury advisors, to ensure best advantage is taken of this quality credit rating.

 

A further performance report will be provided after the end of the September 2018 quarter.

 

5.         Compliance and administration

 

Does the Committee have delegated authority to decide?

Yes

Are the decisions significant?

No

If they are significant do they affect land or a body of water?

No

Can this decision only be made through a 10 Year Plan?

No

Does this decision require consultation through the Special Consultative procedure?

No

Is there funding in the current Annual Plan for these actions?

Yes

Are the recommendations inconsistent with any of Council’s policies or plans?

No

The recommendations contribute to Goal 5: A driven and enabling Council

 

The recommendations contribute to the outcomes of the Driven and Enabling Council Strategy

 

The recommendations contribute to the achievement of action/actions            Not Applicable

 

Contribution to strategic direction

Routine

 

 

 

Attachments

1.

Schedule 1 - Debt levels & prudential borrowing ratios    
Schedule 2 - Interest rate swaps
Schedule 3 - Risk exposure position

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator



 

 

 


PALMERSTON NORTH CITY COUNCIL

 

Committee Work Schedule

TO:                                Finance and Performance Committee

MEETING DATE:           20 August 2018

TITLE:                            Committee Work Schedule

 

 

RECOMMENDATION(S) TO Finance and Performance Committee

1.   That the Finance and Performance Committee receive its Work Schedule dated August 2018.

 

 

Attachments

1.

Committee Work Schedule

 

    


PDF Creator